Xcel Energy has made good progress in fixing their interconnection process for homes under construction. They are working on an automated, long-term solution and are implementing a manual solution for the interim. The following process steps will be necessary only until the planned adjustments are made in the interconnection application portal in the third quarter. Xcel Energy will notify customers when the more automated process is available and the changes in procedures that will need to be followed at that time. For now, the three-step process will work as follows: